Hi Guys
The element guys have been busy building up the track this week. We are currently at 75% completion with only remaining work to be
Section 11. Rebuilding of the rock garden.
2. Earth works at location to drop into rock garden.
Section 21. Smoothening/Resurfacing of the 4x section of the track.
2. Reshaping of the berms and table tops.
After the above
We will be cleaning up the track + marking and also rebuild the old track + shape the dirt jump track :)
Target completion is by 31st December 2009 :)Anyway track is open now, but be aware of signage and
WALK THE TRACK BEFORE TRYING ANY OBSTACLE.Keep it clean too !
Cheers
Some pics of the guys working on the track

2nd Drop Completed and the drop almost done..

The gang working on the planks for the drop.

Aziz, Shahril & Man working on strengthening the drop. Acai, arranging the planks.

Arguing on the alignment ! Engineers at work. Team work. It took 6 guys 2 hours to complete this.

Whatever it is .. There should always be style ! Man nailing it... literally.

Acai literally using the head to work on the drop. Aziz digging for gold ! 1 man working the rest mandor !

Run up to the drop at rock garden & View from the drop at the rock garden

Previous exit to rock garden & View of the drop at the rock garden (Work in progress 12/12/2009)

8ft gap after berm (upgraded from previous gap of 5 feet.) & Receiver after gap

Another gap rebuilding in progress. The track builders taking a breather and discussing whats next ? :)

resurfacing works of the receiver+berm after the gap :) > Azman hard at work
The vid of the guys building the drop.