The element guys have been busy building up the track this week. We are currently at 75% completion with only remaining work to be
Section 1
1. Rebuilding of the rock garden.
2. Earth works at location to drop into rock garden.
Section 2
1. Smoothening/Resurfacing of the 4x section of the track.
2. Reshaping of the berms and table tops.
After the above
We will be cleaning up the track + marking and also rebuild the old track + shape the dirt jump track :)
Target completion is by 31st December 2009 :)
Anyway track is open now, but be aware of signage and WALK THE TRACK BEFORE TRYING ANY OBSTACLE.
Keep it clean too !
Cheers
Some pics of the guys working on the track
2nd Drop Completed and the drop almost done..
The gang working on the planks for the drop.
Aziz, Shahril & Man working on strengthening the drop. Acai, arranging the planks.
Arguing on the alignment ! Engineers at work. Team work. It took 6 guys 2 hours to complete this.
Whatever it is .. There should always be style ! Man nailing it... literally.
Acai literally using the head to work on the drop. Aziz digging for gold ! 1 man working the rest mandor !
Run up to the drop at rock garden & View from the drop at the rock garden
Previous exit to rock garden & View of the drop at the rock garden (Work in progress 12/12/2009)
8ft gap after berm (upgraded from previous gap of 5 feet.) & Receiver after gap
Another gap rebuilding in progress. The track builders taking a breather and discussing whats next ? :)
resurfacing works of the receiver+berm after the gap :) > Azman hard at work
The vid of the guys building the drop.